Police Headquarters

Last updated: September 7, 2026

The city is choosing where to build a new police headquarters. No final site has been selected, and the leading option raises an unresolved question about the City Charter.

Updated as new information is verified — check back often.

Current Status — as of September 2026

1. Where things stand now

No final site has been chosen. No traffic study or environmental study has started for any site being considered. CONFIRMEDcity's own project FAQ page [1]

Civic Center Park is currently the leading option. Councilmembers Noah Blom and Erik Weigand have publicly said they support it. STATEDon-record statements, Voice of OC [14]

On August 31, 2026, the Sierra Club’s Orange County Conservation Committee (part of its Angeles Chapter) sent a letter opposing the Civic Center Park site. CONFIRMEDletter received and included in Sept 2, 2026 agenda packet [20] The letter raised concerns about habitat loss, wetlands, and an underground aquifer. It asked the city to compare alternative sites openly before making a final decision. STATEDclaims attributed to the Sierra Club [20]

The 870 Santa Barbara Drive site is no longer being actively studied. On July 21, 2026, the Advisory Committee voted 5-0 to recommend that the City Council stop spending staff time and money studying that location. The committee said this vote does not rule out studying the site again in the future. CONFIRMEDAdvisory Committee meeting minutes, July 21, 2026 [21]

2. How we got here

  • November 2022: Council approved the $30.5 million purchase of 1201 Dove Street as a future site. CONFIRMEDstaff report, Legistar [3]
  • A proposal for a fully public process was voted down. The Council then formed a 3-member Ad Hoc Committee. CONFIRMEDCity staff presentation, March 10, 2026 [4]
  • Four resident members were confirmed to the broader 7-member Advisory Committee: Thomas Maloney, Sandra Meadows, Robert Olson, and Paul Watkins. A total of 31 applications were received for the four resident seats. CONFIRMEDCity Council Staff Report, June 23, 2026, Agenda Item No. 20 [17] Ron Rubino was originally put forward as the fourth resident member. His nomination was challenged at the meeting. The Council voted to remove him. Councilmember Robyn Grant was the sole member not comfortable joining the removal. Paul Watkins was seated in Rubino’s place. REPORTEDStu News Newport; the June 23, 2026 meeting minutes remain in Draft status as of this writing [5]
  • July 28, 2026: Council approved three consultant contracts for the Civic Center site evaluation: LPA, Inc. for conceptual design, EPD Solutions for environmental review, and Westbound Communications for public outreach. About $1.5 million is approved and funded so far; the full contract ceiling could grow to about $13.1 million if every future phase is approved. See the July 28, 2026 timeline entry for the full breakdown. CONFIRMEDCity Council Staff Report, July 28, 2026, Agenda Item Nos. 18, 19, 20 [19]

3. Next milestone

The Police Headquarters Advisory Committee held its third meeting on September 2, 2026. CONFIRMEDAdvisory Committee agenda packet, September 2, 2026 [20] The meeting was expected to take up the 12 Corporate Plaza candidate site; the outcome has not yet been independently confirmed against the packet's contents, and none is asserted here.

4. Open question

The city’s Charter (its own set of governing rules) says most city administrative offices must be located at the Civic Center. Voters added that rule in 2008 (Measure B) and changed it in 2012 (Measure EE). [20] [21] Does a police station and jail count as an “administrative office” under that rule? No public legal opinion has answered this question yet. UNCONFIRMEDopen question — not yet answered by any public document found

Advisory Committee roster, as confirmed by the City Council on June 23, 2026

Councilmembers

  • Sara Weber
  • Michelle Barto
  • Mayor Pro Tem Noah Blom

Resident members

  • Tom Maloney
  • Sandy Meadows
  • Bob Olson
  • Paul Watkins

The City Council confirmed this roster on June 23, 2026, as the membership of the Police Headquarters Advisory Committee. CONFIRMEDCity Council action, June 23, 2026[7] The City received 31 applications for the four resident seats. CONFIRMEDCity Council staff report, June 23, 2026, Agenda Item No. 20[17]

Advisory Committee voted to stop studying the current 870 Santa Barbara Drive site

At its July 21, 2026 meeting, the Police Headquarters Advisory Committee voted 5-0 to recommend that the City Council cease expending further staff time and resources studying the 870 Santa Barbara Drive site. Vice Chair Noah Blom made the motion; Councilmember Michelle Barto seconded it. Chair Sara Weber clarified the motion was to stop spending resources at this time, not to permanently foreclose future consideration of the site. CONFIRMEDAdvisory Committee meeting minutes, July 21, 2026 (Attachment A, Sept 2, 2026 agenda packet) [21]

The committee cited operational constraints identified in prior council review. The motion means the three Santa Barbara Drive rebuild and renovation options shown in the site comparison below are no longer under active study by the committee.

This item was previewed in the City's “From City Hall to You” newsletter, received and published by Stu News Newport on July 17, 2026. REPORTEDCity newsletter content as carried by Stu News Newport, July 17, 2026[16]

⚠ DISCREPANCY Two checkable records conflict on whether a sale of the Santa Barbara Drive property has been discussed.

  • Handwritten notes from the November 18, 2025 Ad Hoc Committee meeting, authored by James Houlihan, Deputy Public Works Director, show a sale and lease-back of the Santa Barbara Drive property to The Irvine Company being discussed. CONFIRMEDPublic Records Act-released document supplied by Keith Curry[28]
  • The City's August 3, 2026 letter to OCTA states that the City Council “has not discussed” selling that property. CONFIRMEDCity correspondence, August 3, 2026[29]

This has not been independently resolved. If you can help us stay current, please let us know.

Neither document has a verified public URL, so no links are provided.

  • The current Santa Barbara Drive building is 49,284 sq ft, built in 1973, and received a 2021 Facilities Condition Assessment rating of "Fair."
  • Since the 2021 assessment, recent system failures include sewer backups, electrical/fire concerns, and a generator switchgear failure.
  • The building does not meet current seismic standards for "essential" facilities (police, fire, hospitals).
  • Only about 20% of the building's interior space has natural light.
  • The facility was not designed for modern policing technology needs — data storage, servers, secure networks, and body-worn camera / digital evidence storage.

CONFIRMEDCity of Newport Beach — March 10, 2026 Council Planning Session, Item No. 2 (Public Works staff presentation)[13]

Site comparison — the six options staff presented to Council, with cost and timeline estimates

Current Site (Santa Barbara) — Option 1: Renovate + Expand

Land
None
Construction
$152M
Total
$157M–$172M
Timeline
~6–7 years
Location
Near Civic Center

Current Site (Santa Barbara) — Option 2: New 2-Story

Land
None
Construction
$161M
Total
$166M–$181M
Timeline
~6 years
Location
Near Civic Center

Current Site (Santa Barbara) — Option 3: New 3-Story

Land
None
Construction
$168M
Total
$173M–$188M
Timeline
~6–7 years
Location
Near Civic Center

1201 Dove Street

Land
None (City-owned)
Construction
~$150M (incl. demolition)
Total
~$150M
Timeline
~3–4 years
Location
Airport Area (not central; increased response times)

Private Land Near Civic Center

Land
$80M–$90M
Construction
~$153M
Total
~$233M–$243M
Timeline
~3–4 years
Location
Near Civic Center

Civic Center Park

Land
None (City-owned)
Construction
~$162M (excl. mitigation)
Total
~$162M
Timeline
~3–4 years
Location
Civic Center Campus

⚠ DISCREPANCY Two City-produced documents give the Civic Center Park cost estimate as $162 million, but they do not agree on what that figure excludes. A January 31, 2026 Advisory Committee planning presentation states the $162 million design/construction estimate is “(excluding significant mitigation).” [26] A subsequent public mailer distributed by the City's PR firm states the same $162 million figure without that caveat. [27] The City's official project FAQ separately notes that “current ranges span from approximately $150 million to more than $240 million, depending on the site evaluated... additional analysis and design work will further refine the numbers,” but does not specify what the unrefined mitigation costs might add to the Civic Center Park estimate specifically. [1] This has not been independently resolved. If you can help us stay current, please let us know.

Read the documents yourself: January 31, 2026 presentation slide · City mailer

The key open question posed by staff on March 10, 2026

"Should the City continue investing in major system upgrades in a building at the end of its useful life?"

Posed verbatim by Public Works staff to the City Council at the March 10, 2026 Planning Session. CONFIRMEDMarch 10, 2026 Council Planning Session, Item No. 2[13]

The timeline: from a 1973 shared facility to a still-undecided 2026 site

  1. Jul 28, 2026

    Council approves Civic Center Park consultant contracts

    The City Council approved consultant contracts tied to the Civic Center Park site. The City’s own “On the Agenda” preview for the July 28, 2026 meeting confirms the three contracts — an agreement for the project’s architectural team, an environmental consultant, and a public outreach and communications consultant — were on the Council agenda. The same preview also confirms the meeting included the 1300 Dove Street Townhome Project (132-unit, for-sale residential) as a separate item. CONFIRMEDCity of Newport Beach City Manager's Office "Insider's Guide" / "On the Agenda" preview [20] Approximately $1,524,410 is currently funded and authorized to proceed: LPA, Inc. Phase 1a conceptual design ($713,080), EPD Solutions SEIR ($346,330), Westbound Communications outreach ($315,000), and an LSA Associates on-call agreement amendment for related biological survey work ($150,000). CONFIRMEDCity Council Staff Report, July 28, 2026, Agenda Item Nos. 18, 19, 20[19] The full potential contract ceiling, if all future phases are authorized, is approximately $13,121,150 — driven primarily by LPA, Inc.'s total not-to-exceed architectural contract of $12,459,820 (covering Phase 1a design through final construction documents and construction support, most of which requires separate future City Council authorization), plus EPD Solutions ($346,330) and Westbound Communications ($315,000). CONFIRMEDCity Council Staff Report, July 28, 2026, Agenda Item Nos. 18, 19, 20[19]

    These two figures are not in conflict — they answer different questions. $1,524,410 is what is funded and authorized now; $13,121,150 is the total possible size of the contracts if every future phase were to be fully exercised. Councilmember Robyn Grant opposed all three of the originally reported contracts, and Councilmember Joe Stapleton joined her in opposing only the communications contract. REPORTEDHoodline report citing the Los Angeles Times [18]
    CONFIRMEDcontract approvals and agenda presence confirmed by City sources; dollar figures and vote-dissent details reported by Hoodline/LA Times
  2. Jul 21, 2026
    Second meeting of the Advisory Committee, focused on evaluating rebuilding at the current Santa Barbara Drive site (per Chair Weber's direction at the July 7 meeting).
    CONFIRMEDofficial agenda
  3. Jul 7, 2026

    First Advisory Committee meeting

    CONFIRMEDofficial agenda First meeting of the Advisory Committee, held in the Civic Center Community Room. Unlike other recent City committees (e.g., the General Plan Advisory Committee, the Lower Castaways and Aquatic Facility Committee), this meeting was not video recorded for public posting.

    REPORTEDdrawn from written meeting materials, not a recording or transcript Resident member Sandy Meadows was absent. The committee received staff briefings on the history of the City’s past police stations and the current headquarters’ operational needs. Chair Sara Weber set the July 21 meeting’s focus on evaluating rebuilding at the current Santa Barbara Drive site. Committee member Paul Watkins raised questions about financing plans and ground-lease options for the Santa Barbara and Dove Street properties, and asked that the 12 Corporate Plaza site be reconsidered. Committee member Tom Maloney recommended staff attend an International Association of Chiefs of Police training on planning, designing, and constructing police facilities. [11]
    CONFIRMEDmeeting occurred per agenda; discussion details are REPORTED from written materials
  4. Jun 9, 2026

    Adopted Capital Improvement Program funding

    The City’s adopted Capital Improvement Program sets aside $1.5 million in the current fiscal year for further study of the Civic Center Park site, $15 million in FY2027–2028 for final design, and $146 million in FY2028–2029 for award of a construction contract. This timeline has been moved up by roughly three years compared to the prior CIP. No explanation for the acceleration has been located in the CIP documents themselves; if a source is later confirmed, this will be updated. [21] [12]
    CONFIRMEDCity Council Resolution No. 2026-40, adopted June 9, 2026
  5. Jun 1, 2026
    Resident-member application deadline.
    CONFIRMED
  6. May 13, 2026

    Speak Up Newport forum exchange

    Former Mayor Keith Curry presented a detailed case against the Civic Center Park site at a Speak Up Newport public forum. Per the Stu News Newport columnist's account, Councilmember Blom's response was reported as "Everything Keith said is wrong," with no further explanation given. Watch the full exchange: Speak Up Newport, May 13, 2026. [9] [10] This quote is sourced to a single columnist's account, not an official transcript or recording.
    STATEDcolumnist's account; primary event page available
  7. May 12, 2026

    Council transitions to a new Police Headquarters Advisory Committee

    The City Council unanimously approved transitioning from the prior council-only Assessment Committee to a new Police Headquarters Advisory Committee: 3 councilmembers plus 4 resident members — one with construction / real estate development / architecture / land-use experience, one with real estate financing experience, and two at-large seats with no specialized requirement — to evaluate location, design, and budget and recommend back to the full council. Resident applications closed June 1, 2026, and a committee meeting was scheduled for July 21, 2026.
    CONFIRMEDCity Council action & resident-committee announcement, May 12, 2026
  8. Mar 10, 2026
    City Council held a study session. Council unanimously agreed the current headquarters (built 1973) needs replacing, citing plumbing, electrical, and infrastructure issues. The Civic Center sculpture garden site emerged as a leading candidate (estimated ~$162 million), though no final site decision was made. Staff was directed to continue evaluation through design work, environmental review, cost analysis, and public input.
    CONFIRMED
  9. Jan–Mar 2026
    The council held planning sessions on police headquarters site options. Traffic, environmental review, and cost analysis were all noted as still pending.
    CONFIRMEDcity project page
  10. Oct 14, 2025

    The fully public process was voted down

    The City Council voted on Stapleton's September 23 proposal. Councilmember Weigand pulled the item; Councilmember Blom offered a substitute motion removing public members and creating the closed, council-only Newport Beach Police Headquarters Assessment Committee (Blom, Weber, Barto) instead. Passed 5–1: Blom, Weigand, Kleiman, Weber, Barto voting yes; Robyn Grant the sole no vote; Stapleton abstaining. The Assessment Committee subsequently met privately to discuss site options. [8] [4]
    CONFIRMEDLegistar staff report, October 14, 2025 (Resolution No. 2025-65)
  11. Sep 23, 2025
    Then-Mayor Joe Stapleton proposed a fully public site-selection process, including making all committee meetings open to the public. [8]
    CONFIRMEDCity Council staff report / minutes
  12. Dec 2022
    New councilmembers (Stapleton, Weigand, Grant, Kleiman) took office; they were not involved in the Dove Street decision.
    CONFIRMED
  13. Nov 2022
    The City Council (Muldoon, Blom, Dixon, Avery, Duffield, Brenner, O'Neill) approved a $30.5 million purchase of 1201 Dove Street as a future police headquarters site.
    CONFIRMEDstaff report, Legistar
  14. 2013
    City Hall moved from its 1948 building on Newport Blvd. to the current Civic Center. The project's cost rose from $105 million to $140.2 million during construction; a later audit found potential overbilling, and the contractor returned $365,000.
    REPORTED
  15. Nov 2012
    Newport Beach voters approved Measure EE, amending the 2008 Charter provision to require most (rather than all) administrative offices to be located at the Civic Center parcel, alongside a number of other Charter housekeeping changes.
    CONFIRMEDCity Attorney's Impartial Analysis; codified Charter text
  16. Feb 5, 2008
    Newport Beach voters approved Measure B, adding a Charter provision requiring City Hall, including the City's administrative offices, to be located on the Civic Center parcel. The amendment took effect March 3, 2008.
    CONFIRMEDMeasure B official text; Charter amendment record
  17. 1973
    The city acquired the Santa Barbara Drive site and built a shared Police/Fire Station 3 facility there.
    CONFIRMED

Sources for this timeline: the Sep 23, 2025 public-process proposal and the Oct 14, 2025 vote [8] [4], the May 13, 2026 Speak Up Newport forum exchange [9] [10], the July 7, 2026 Advisory Committee meeting [11], and Resolution No. 2026-40 adopting the Capital Improvement Program funding [21] [12].

Newport Beach Police Association: publicly opposed to remodeling the current site

The Newport Beach Police Association has publicly stated that remodeling, reconstructing, or reusing the current Santa Barbara Drive site is not an option it supports. In its stated position, the Association cites the station's age — built more than five decades ago — and its inability to reliably support evidence logging, officer operations, and emergency response for a population that has roughly doubled since it was built. STATEDNewport Beach Police Association public statement[15]

The case each side has made, in their own words

For the Civic Center Park site

Councilmember Blom

In a recorded interview: "I don't want to go out for a bond measure, I don't want to put this all on taxpayers." He also described it as "the final piece to wrap up the civic center," and, addressing the loss of sculpture garden space directly: "I have a three year old daughter, we walk every park in this city and she does love the sculpture garden. But sometimes I have to weigh fiscal responsibility at the same spot. It just seems to be the most responsible way."[14]

STATEDVoice of OC

Councilmember Weigand

In a written statement: "With two high-profile and significant incidents occurring within months of one another at Fashion Island, it became imperative to me (and others) that we must keep our department's headquarters in and around Newport Center."[14]

STATEDVoice of OC

Councilmember Weber

Stated she wants the station to remain centrally located, and separately asked staff to look at ways to preserve the sculpture garden rather than treating the tradeoff as all-or-nothing.[14]

STATEDVoice of OC

City staff cost comparison

Civic Center Park is estimated at roughly $162 million. Purchasing an additional nearby property instead would likely push the cost above $233 million. Rebuilding at the current Santa Barbara Drive site would nearly double the project timeline, pushing completion into the 2030s.[6]

CONFIRMEDcity staff report, as reported by Voice of OC

Raising concerns about the process or site

Councilmember Stapleton

Who had proposed the fully public process that was voted down, said afterward: "I think this is going to become one of the most expensive buildings in the history of our city," while also saying of the current Advisory Committee, "I do think the committee is doing a good job now getting out in the public and this will be that first opportunity."[14]

STATEDVoice of OC

Councilmember Grant

Was the sole vote in favor of a fully public process from the start, and has cited the risk of delays from environmental review or litigation tied to the 2007 ballot measure.

STATEDstated / confirmed — vote record

Former Mayor Keith Curry

Has publicly opposed the Civic Center Park site in a moderated public debate.

REPORTED

Sierra Club, Angeles Chapter (Orange County Conservation Committee)

Submitted a letter to the City Council and Advisory Committee opposing the Civic Center Park site, citing habitat fragmentation, wetlands, and an underground aquifer, and requesting a transparent comparison of alternative sites before any final decision. [20]

CONFIRMEDletter submitted Aug 31, 2026 STATEDecological claims attributed to the Sierra Club

Resident Jim Mosher and others

Have raised questions about the Campus Drive purchase price and site-selection reasoning discussed in the Fire Station section of this site.

STATED

Notes & Sources

Numbered references for the claims above. Numbering restarts on each page. How claims are labeled →

  1. [1]

    City of Newport Beach — police headquarters project FAQ

    No final site has been chosen and no traffic or environmental study has begun for any site under consideration.

  2. [2]

    Newport Beach City Charter (codified text)

    The Charter provision added by Measure B (approved February 5, 2008, effective March 3, 2008) and amended by Measure EE (approved November 2012), which requires most of the City's administrative offices to be located on the Civic Center parcel.

  3. [3]

    City staff report / Legistar

    The November 2022 council approval of the $30.5 million purchase of 1201 Dove Street.

  4. [4]

    City of Newport Beach — Legistar staff report, October 14, 2025: "Resolution No. 2025-65: Creating the Newport Beach Police Headquarters Assessment Committee"

    The October 14, 2025 formal creation of the Newport Beach Police Headquarters Assessment Committee (Blom, Weber, Barto), the vote against a fully public process, and Robyn Grant's dissent.

  5. [5]

    Stu News Newport

    Confirmation of the four resident committee members, the Rubino application question, and the noted appearances of potential conflict.

  6. [6]

    City staff cost comparison, as reported by Voice of OC

    Cost estimates: ~$162M for Civic Center Park, above $233M for an added nearby property, and a near-doubled timeline for a Santa Barbara Drive rebuild.

  7. [7]

    City of Newport Beach — City Council action, June 23, 2026

    The confirmed roster of the Police Headquarters Advisory Committee: Councilmembers Sara Weber, Michelle Barto, and Mayor Pro Tem Noah Blom; resident members Tom Maloney, Sandy Meadows, Bob Olson, and Paul Watkins.

  8. [8]

    City of Newport Beach — Legistar staff report, October 14, 2025: "Resolution No. 2025-65: Creating the Newport Beach Police Headquarters Assessment Committee"

    September 23, 2025 proposal by then-Mayor Joe Stapleton for a fully public police headquarters site-selection process, and the October 14, 2025 vote on the substitute motion creating the council-only Newport Beach Police Headquarters Assessment Committee (Blom, Weber, Barto), passed 5–1 with Grant opposed and Stapleton abstaining.

  9. [9]

    Stu News Newport — column, May 2026

    Columnist's account of the May 13, 2026 Speak Up Newport public forum, including the reported 'Everything Keith said is wrong' response attributed to Councilmember Blom.

  10. [10]

    Speak Up Newport — event page

    Primary-source record of the May 13, 2026 'New Police Station 2026' forum featuring former Mayor Keith Curry and Councilmember Noah Blom.